West Ells CPF Earthworks

This project consisted of site preparation, earthworks excavation and fill, storm water pond and gravity drain construction.




Client:

Sunshine Oilsands Ltd

Project Location:

60 km West of Fort McKay, Alberta

Major Quantities:

Topsoil, Subsoil, Stripping, muskeg removal - 206,800 m3
General Excavation - 280,000 m3
Borrow Excavation - 125,800 m3
Common Fill - 312,100 m3
Geotextile - 9,000 m2

Contract Type:

Unit Price & Hourly

TBCLP Role:

General Contractor

Contract Awarded:

August 2012

Work Commenced:

August 2012

Work Completed:

September 2013