Suncor Firebag Stage 3+ Firebag Village
This project consisted of new campsite construction, muskeg stripping, roads, ditching, geotextiles and granular surfacing.
Client:
Suncor Energy Inc.
Project Location:
Suncor Firebag Village - 140 km north of Fort McMurray
Major Quantities:
Muskeg Stripping - 220,000 m3
Overburden - 132,000 m3
Clay Fill - 440,000 m3
Ditch Excavation - 9,500 m3
Granular Surfacing - 7,000 m3
Geotextiles - 48,000 m2
Contract Type:
Reimbursable Hourly Contract
TBCLP Role:
General Contractor
Contract Awarded:
February 2007
Work Commenced:
March 2007
Work Completed:
July 2007
Project Duration:
134 Days
Number of Workers:
Up to 300
All Projects
- Suncor Firebag Stage 3+ Aerodrome & Access Road
- Suncor Firebag Stage 3+ Firebag Village
- Suncor Firebag Well Pads 105, 106 & Access Road
- Suncor Firebag Well Pads 107, 108 & Access Road
- Suncor Firebag Stage 3+ Plant 93 Expansion
- Nexen Well Pad 9111 & Access Road
- Plant 300 Access Road from Steepbank Trail
- Sunrise Thermal Project - Early site Development