Suncor Firebag Well Pads 105, 106 & Access Road

This project consisted of the construction of 2 well pads and 2.6 km of access roads within Suncor Firebag Stage 3+.




Client:

Suncor Energy Inc.

Project Location:

Suncor Firebag - 140 km north of Fort McMurray

Major Quantities:

Geotextiles & GeoGrid - 415,400 m2
Wick Drains - 107,300 m
Engineered Fill - 175,850 m3
Clay Fill - 246,860 m3
40mm Granular - 77,465 m3
20mm Granular - 3,000 m2

Contract Type:

Budget Hourly

TBCLP Role:

General Contractor

Contract Awarded:

April 2007

Work Commenced:

May 2007

Work Completed:

September 2007

Project Duration:

150 Days

Number of Workers:

Up to 150 (double shift)