Plant 300 Access Road from Steepbank Trail
This project consisted of the construction of 2.4 km of access road to Plant 300 as well as Well Pad accesses.
Client:
Suncor Energy Inc.
Project Location:
Suncor Minesite - 20 km north of Fort McMurray
Major Quantities:
Clearing & Grubbing - 9.44 ha
Stripping - 14,160 m3
Common Excavation - 140,000 m3
Engineered Fill - 113,400 m3
Granular Surfacing - 106,000 m3
Topsoil Placement - 74,000 m2
Contract Type:
NA
TBCLP Role:
NA
Contract Awarded:
NA
Work Commenced:
NA
Work Completed:
On-going
Project Duration:
NA
Number of Workers:
NA
All Projects
- Suncor Firebag Stage 3+ Aerodrome & Access Road
- Suncor Firebag Stage 3+ Firebag Village
- Suncor Firebag Well Pads 105, 106 & Access Road
- Suncor Firebag Well Pads 107, 108 & Access Road
- Suncor Firebag Stage 3+ Plant 93 Expansion
- Nexen Well Pad 9111 & Access Road
- Plant 300 Access Road from Steepbank Trail
- Sunrise Thermal Project - Early site Development