Nexen Well Pad 9111 & Access Road

Construction of Well Pad 9111 including Access Road and Flow Lines. Musket removal, stripping topsoil zones and cut to fill.




Client:

Nexen Inc. - Long Lake Project

Project Location:

Anzac - 150 km south of Fort McMurray

Major Quantities:

Common Excavation - 297,000 m3
Topsoil & Muskeg Excavation - 66,000 m3
Granular Placement - 15,200 m3

Contract Type:

Unit Rate Contract

TBCLP Role:

Prime Contractor

Contract Awarded:

May 2008

Work Commenced:

June 2008

Work Completed:

September 2008

Project Duration:

120 Days

Number of Workers:

Up to 30