Nexen Well Pad 9111 & Access Road
Construction of Well Pad 9111 including Access Road and Flow Lines. Musket removal, stripping topsoil zones and cut to fill.
Client:
Nexen Inc. - Long Lake Project
Project Location:
Anzac - 150 km south of Fort McMurray
Major Quantities:
Common Excavation - 297,000 m3
Topsoil & Muskeg Excavation - 66,000 m3
Granular Placement - 15,200 m3
Contract Type:
Unit Rate Contract
TBCLP Role:
Prime Contractor
Contract Awarded:
May 2008
Work Commenced:
June 2008
Work Completed:
September 2008
Project Duration:
120 Days
Number of Workers:
Up to 30