Kearl - Athabasca Field Program

This project consisted of the clearing and freezing down of Kearl, Syncrude & Firebag.




Client:

Fluor Canada Ltd

Project Location:

120 km Northeast of Fort McMurray, Alberta

Major Quantities:

Access Roads
41 km of New Winter Access Trials
458km of Existing Access Trials
112 Watercourse Crossings
1 Engineered River Ice Bridge
404 Well Pad Leases
Reclamation / Roll Back of above
General supply service for the entire site

Contract Type:

Hourly

TBCLP Role:

General Contractor

Contract Awarded:

October 2009

Work Commenced:

November 2009

Work Completed:

March 2010

Project Duration:

135 Days

Number of Workers:

Up to 120 (including night shift)