This project consisted of the re-routing of the Main Plant Access Road (MPAR) .




Client:

Imperial Oil Resources

Project Location:

120 KM NE of Fort McMurray

Major Quantities:

12 km Road Project with 6 minor and 1 major stream crossings
Earthworks Cut - 734,300 m3
Earthworks Fill - 671,900 m3
Geogrid - 355,400 m2
Geotextile - 190,400 m2
Road Culvert - 560 lm
Stream Crossing - 280 lm
Muskeg Removal - 51,800 m3

Contract Type:

Lump Sum

TBCLP Role:

General Contractor

Contract Awarded:

May 2014

Work Commenced:

May 2014

Work Completed:

On going

Project Duration:

TBA

Number of Workers:

TBA