Horizon Project Recycle Pond
This project consisted of excavating and placement of engineered fill for the recycle pond at CNRL.
Client:
Canadian Natural Resources Limited
Project Location:
Horizon Project - 120 km north of Fort McMurray
Major Quantities:
Waste Excavation - 42,000 m3
Dyke Liner - 100,000 m3
Sand Fill - 75,000 m3
Clay Fill - 130,500 m3
Contract Type:
Reimbursable Hourly Contract
TBCLP Role:
Contractor
Contract Awarded:
April 2006
Work Commenced:
May 2006
Work Completed:
October 2006
Project Duration:
6 Months
Number of Workers:
NA
All Projects
- Suncor Firebag Stage 3+ Aerodrome & Access Road
- Suncor Firebag Stage 3+ Firebag Village
- Suncor Firebag Well Pads 105, 106 & Access Road
- Suncor Firebag Well Pads 107, 108 & Access Road
- Suncor Firebag Stage 3+ Plant 93 Expansion
- Nexen Well Pad 9111 & Access Road
- Plant 300 Access Road from Steepbank Trail
- Sunrise Thermal Project - Early site Development