East Athabasca Highway and Bridges

This project consisted of construction of the East Athabasca Highway including several bridges and bridge culverts.




Client:

Suncor Energy

Project Location:

100 km Northeast of Fort McMurray, Alberta

Major Quantities:

Grading, Base Course and Lean Oil Sands Construction
Material handling and staging
Highway Construction - Common / Borrow / Channel topsoil Excavations
Grading, Base Course and Lean Oil Sands Construction
Geotextiles, Culverts, Graveling, Signage and Seeding
3 Bridges / Bridge Culvert Construction - 7 Creek Crossings
Channel Excavation, Frainage Culverts and Erosion Control

Contract Type:

Earthworks: Unit Price, Bridges: Lump Sum

TBCLP Role:

General Contractor

Contract Awarded:

October 2009

Work Commenced:

November 2009

Work Completed:

December 2010

Project Duration:

275 Days

Number of Workers:

Up to 120