Aerodrome Access Roads & Gravel Pit
This project consisted of the design and construction of 9.5 kms of heavy haul road, 4.5 kms of access road, and 1 major bridge structure.
Client:
Canadian Natural Resources Limited
Project Location:
25 km north of Fort MacKay
Major Quantities:
Common Excavation - 1,400,000 m3
Borrow Excavation - 150,000 m3
Contract Type:
Competitive Lump Sum
TBCLP Role:
Contractor
Contract Awarded:
January 24, 2004
Work Commenced:
February 2005
Work Completed:
July 2005
Project Duration:
72,000 Hours
Number of Workers:
60